Leat Diversion Pump Chamber

Overview

December 2020 saw heavy rainfall lead to Charlestown’s 300 year old leat burst its banks, localised flooding, and the subsequent closure of the Eden Project. We Are Ease were mobilised to conduct emergency flood response by over pumping the surface water to the connecting leat 400m away. Once the site was made safe and local hydrology stabilised, a permanent emergency pumping solution could be designed.
Following the design phase, excavation in hard material commenced to facilitate the installation of a reinforced concrete pump chamber. Concurrent trenching, rising main, and electrical sub-main installations were then completed to commission the pump sets and electrical control panel. Final silt trap, screen, mezzanine floor, and headwall installations then allowed for the successful releasing of the leat water once again. Leaving the Eden Project more resilient to heavy rainfall and flooding in the future.
Eden Project leat diversion pump chamber by We Are Ease Ivybridge Devon
Eden Project leat diversion pump chamber by We Are Ease Ivybridge Devon
Eden Project leat diversion pump chamber by We Are Ease Ivybridge Devon

Key Project Stages

Emergency Flood Response
Leat Diversion Over Pumping
Earthworks
Reinforced Concrete Pump Chamber Construction
Rising Main Installation
Silt Trap Construction, Screen, and Mezzanine Fabrication/Installation
Submersible Pump Installation
Mechanical Connection
Electrical Control Pannel Installation and Connection
Testing, Commissioning, and Successful Leat Diversion
Scroll to Top

Are you in the early stages of planning your building, but not quite sure how best to move it forward? As the leading construction management provider in the south west, we can assist you with your how to get things moving; feasibility; advise you an unbiased realistic budget based on current market conditions; advise what your budget might achieve for you; introduce you to the right level of specialist design required, from architects to landscape; where cost is limiting you taking things forward, we can identify value engineering to see if we can bring you savings to meet your budget, without limiting your aspirations and goals.

Contact us today.

Alternatively, speak with one of the team, Senior Manager Andrew Doidge, direct on 07484 035027 to discuss your requirements further.

Growing Point, Eden Project

Got the planning and are ready to go, but have been somewhat disheartened by the costs being returned by the builders tendering? Come to us – construction management can bring massive savings over traditional building. We identify the savings for the benefit of you and your build, as opposed to increasing the profit of the builder.

Contact us today.

Alternatively, speak with one of the team, Senior Manager Andrew Doidge, direct on 07484 035027 to discuss your requirements further.

Harbour Beach Club Hotel & Spa

Fallen out with your builder? Costs spiralling out of control? WAE and construction management is perfectly placed to step in quickly to replace whatever mishap might be currently evolving on your project. Contact us to discuss how we can help. Ease and CM can most likely remobilise things quicker than you are identifying and involving another builder to take over the incomplete works. Difficult events are, they needn’t be as cataclysmic as they might initially seem.

Contact us today.

Alternatively, speak with one of the team, Senior Manager Andrew Doidge, direct on 07484 035027 to discuss your requirements further.

The Neighbourhood, Student Accommodation