The Neighbourhood, Student Accommodation, Exeter

Overview

The Neighbourhood is a 129 bed student accommodation scheme in the centre of Exeter. The developer, Ethos, contacted us April 2019 after their contractor had gone into liquidation along with the Mechanical Contractor. The rooms were generally in a good condition but the roof and envelope were incomplete, the mechanical system needed some work to complete, all systems needed to be commissioned and rooms fitted out and snagged. We were approached by Ethos, on recommendation from Girling Jones, to come in assess all aspects of the project and put together a team to complete the project. Initially there was an intense period as we made contact with all the trade contractors and consultants. Work out who wants to continue, what are the key risks, what site team is needed and pull together a target programme. This was then presented to the client for comment and approval before implementation.
At first dialogue with the client body was daily but once the plan was in place we reverted to fortnightly meeting with the client, design team and funders. You’ll be pleased to know that the scheme was completed in August 2019, including attaining BREEAM accreditation, and occupied by the new intake of students in September 2019. We are now supporting Ethos on a second scheme in Exeter using the same site management team. Hope that gives you a taste of the type of thing we do when we take over a distressed project.
The Neighbourhood Student Accommodation Exeter Devon
The Neighbourhood Student Accommodation Exeter Devon

Key Project Stages

Original Contractor went into Liquidation
Devise strategy to complete the project
Assembly of delivery team
Disputes resolution
Problem solving
James Kenedy, Investment Manager, said:
“We Are Ease were brought in to the project at a point when the main contractor had fallen into administration and we had secured control of the site. We needed a firm with an established reputation who would be able to draw on local connections at short notice. They also needed to have a keen eye for both the commercial and the practical requirements of stepping in to a long and varied list of unfinished sub-contract packages and to lead a team on site with our support in the background. Student Housing is time-critical on delivery, and we needed to very quickly re-mobilize works in order to achieve the August completion date. Works began within 2 weeks of us taking control of the site and started with a considerable amount of backward-looking remediation of defective works left by the outgoing contractor. We Are Ease led the negotiations with all the incoming contractors and were able to secure the return of those who had previously withdrawn their services. We would not say the project was without its challenges but we were pleased to have the benefit of a close and very effective working relationship with We Are Ease to get it across the line. The scheme opened to incoming students on time and on budget and we did not hesitate to continue the relationship with We Are Ease for the construction of the second phase of the site.”
Scroll to Top

Are you in the early stages of planning your building, but not quite sure how best to move it forward? As the leading construction management provider in the south west, we can assist you with your how to get things moving; feasibility; advise you an unbiased realistic budget based on current market conditions; advise what your budget might achieve for you; introduce you to the right level of specialist design required, from architects to landscape; where cost is limiting you taking things forward, we can identify value engineering to see if we can bring you savings to meet your budget, without limiting your aspirations and goals.

Contact us today.

Alternatively, speak with one of the team, Senior Manager Andrew Doidge, direct on 07484 035027 to discuss your requirements further.

Growing Point, Eden Project

Got the planning and are ready to go, but have been somewhat disheartened by the costs being returned by the builders tendering? Come to us – construction management can bring massive savings over traditional building. We identify the savings for the benefit of you and your build, as opposed to increasing the profit of the builder.

Contact us today.

Alternatively, speak with one of the team, Senior Manager Andrew Doidge, direct on 07484 035027 to discuss your requirements further.

Harbour Beach Club Hotel & Spa

Fallen out with your builder? Costs spiralling out of control? WAE and construction management is perfectly placed to step in quickly to replace whatever mishap might be currently evolving on your project. Contact us to discuss how we can help. Ease and CM can most likely remobilise things quicker than you are identifying and involving another builder to take over the incomplete works. Difficult events are, they needn’t be as cataclysmic as they might initially seem.

Contact us today.

Alternatively, speak with one of the team, Senior Manager Andrew Doidge, direct on 07484 035027 to discuss your requirements further.

The Neighbourhood, Student Accommodation