Watergate Bay Seawall
- Client: Watergate Bay Hotel
- Project Value: £250,000
- Duration: 12 weeks
- Location: Watergate Bay Newquay Cornwall
- Client: Watergate Bay Hotel
- Project Value: £250,000
- Duration: 12 weeks
- Location: Watergate Bay Newquay Cornwall
Overview
The existing RNLI hut and Seawall located at Watergate Bay Newquay, needed a modern, larger facilities and replacement of the sea wall and access steps.
To accommodate the new RNLI lookout and training center, the following phases of construction were required.
• Demolish the existing RNLI building.
• Excavation of the footprint proposed.
• Cliff stabilization works.
• Enabling works in place for substructure.
• New constructed Seawall and access steps.



Key Project Stages
✓ Excavation of 1250m3 into cliff
✓ Rock Anchor system to stabilize cliffs
✓ RC Seawall & steps replacement works